GoSoft Learn
Home›Theory›Module 09

Module 09 · Costs and accounting

The cost of each lot

What makes up a lot's cost (land, studies, permits, development), how it's allocated across lots by area, equal parts or by hand, each sale's direct costs and how GoSoft shows each lot's cost and margin.

⏱ 9 min readLevel: Intermediate

To know how much you earn on each lot you need to know what it cost you. And a lot's cost isn't on any invoice: you have to build it by allocating the project's costs.

By the end of this lesson you will be able to
  • Identify what is part of a lot's cost.
  • Allocate the project's cost across its lots.
  • Read each lot's cost and margin in GoSoft.

What is cost and what isn't

Lot costNot lot cost (it's an expense)
Land purchase and its costs (deed, taxes)Advertising and sales material
Studies, design, surveyingSalespeople's commissions
Permits and approvalsOffice salaries
Development: streets, water, sewer, powerLoan interest (except during the works, per the standard)

How it's allocated

The project's cost is spread across the lots. The most common methods:

MethodWhenExample with 100,000,000 and four lots
By areaLots of similar value per m²250 m² lot out of 1,000 m² = 25,000,000
Equal partsLots of the same size25,000,000 each
ManualVery different lots (corners, views)According to the company's criteria

Each sale can also have direct costs: the deed for that lot, a wall just for it. They're added to its cost.

Margin per lot

LotPriceCostMarginCost over price
Lot 0160,000,00020,000,00040,000,00033 %
Lot 0266,000,00025,400,00040,600,00038 %

In GoSoft, step by step

  1. When recording a purchase for the whole project (for example, the development invoice), open Distribute cost to lots on that line, choose the method and apply the distribution. The difference must be zero.

  2. A contract's expenses are linked in its Expenses and costs tab.

  3. Open Purchasing and costs → Control and costing → Costing by project and lot: each lot with its status, list price, allocated cost, direct costs, total cost and cost over price.

    Costing by lot with cost over price
Price with the cost in view

Before launching a phase or a promotion, check the lots' cost over price. If a discount leaves the margin below what commissions and financing cost, you're selling at a loss.

Self-assessment

Is the salesperson's commission part of the lot's cost?

No. It's a selling expense.

Development of 80,000,000 for 1,000 sellable m². How much goes to a 150 m² lot by area?

80,000 per m² × 150 = 12,000,000.

Where do you see each lot's cost and margin?

In Costing by project and lot.

Next: the entries GoSoft books

▶ Watch it on video

Chapter 46Costing by project and lot